Economy

Liquidated Damages Recovered for Project Delays Constitutes Supply of Services: AAR

The Telangana bench of the AAR has recently ruled that the liquidated damages recovered on account of a delay in the completion of a project constitutes a supply of service under the Goods and Services Tax (GST) Act.

The applicant M/s. Achampet Solar Private Limited was engaged in the production and distribution of electricity obtained from solar energy. The applicant had agreed to the construction of a solar power project.

One of the clauses in the agreement was for liquidated damages in the event of a delay in the commissioning and delivery of the contract. In its application to the AAR, the applicant raised a query as to whether the liquidated damages that could be recovered due to delay in commissioning of the project will be liable to GST. The applicant also sought clarity on the time of supply when the liability to pay GST is triggered.

The AAR held that the liquidated damages claimed by the applicant for the delay in commissioning beyond the agreed time limit constituted consideration for tolerating an act or situation arising out of contractual obligations. This falls under the purview of a supply of service under Schedule II Entry 5(e) of the Central Goods and Services Tax (CGST) Act. Hence, the same would be liable to GST. Being a supply of service, the same would be liable to 18% GST.

Further, with regard to the time of supply of the service, the AAR ruled that the date of determination of liquidated damages will be per the formula prescribed in clause (6) of the agreement. Clause (6) specifies different liquidated damages to be paid for different delay periods in the commissioning. This clause also specifies that the amount should be paid within three days from the actual commissioning date and as per the formula prescribed. Hence, as the contract prescribes the date on which the liquidated damages have to be determined and paid, the date on which the liquidated damages is determined will be the time of supply of the service.

It should be noted that AAR rulings may not set a judicial precedent, but they could have a persuasive effect in similar cases.

For any clarifications/feedback on the topic, please contact the writer at athena.rebello@cleartax.in

Share

Recent Posts

Mutual Funds: SIP Inflows Breach Rs 19,000-Crore Mark for the First Time in February ’24

The systematic investment plan (SIP) contribution in February 2024 has crossed a new milestone. The monthly contribution tipped at Rs…

2 months ago

Income-Tax Return: A Brief Note on Annual Information Statement (AIS)

The Income-Tax (I-T) Department has directed taxpayers to access the Annual Information Statement (AIS) via the e-filing official portal and…

2 months ago

Mutual Funds: All About SIP and Market Fluctuations

Considering the vagaries of the stock market, investors often ponder over reevaluating their strategies. Whether to continue to remain invested…

2 months ago

Income-Tax Saving Through Strategic Life Insurance Planning

Financial planning is beyond just investing wisely to save on taxes; it's also related to protecting oneself and one's loved…

2 months ago

Income-Tax Return: Here’s a Note on Tax-Saving Avenues

A salaried individual earning up to Rs 5-15 lakh as net salary on an annual basis must first take stock…

2 months ago

A Quick Take on Equity-Linked Savings Scheme

Equity-linked savings schemes (ELSS), also referred to as tax-saving schemes, are equity funds that invest a significant portion of their…

2 months ago